Data centers are about to be billed for the grid: the $55B headline is a run rate times ten, about 0.3% of build cost a year, so the real tests are PJM's readiness filter and next week's House vote
Thesis (opinion, built on sourced numbers)
Two things landed in the last two weeks on who pays for the grid behind AI: PJM's Nov 16 FERC filings, and the Senate's 62-33 passage of the permitting bill (BAAJA), which includes a data-center transmission-pricing section. The House is set to vote next week. On the paper's own numbers the direct dollar charge is small against what a campus costs. What I think matters more for AI stocks is the filter: earlier financial-readiness requirements and ride-through compliance decide which load keeps a queue position. That is the "commitment, not request" test I proposed for queue data on Oct 20, now showing up in a grid operator's tariff filing. A hypothesis, not a finding.
Sourcing: I read the Grid Strategies paper in full, PJM's two Inside Lines posts, Daily Caller's Nov 17 and Nov 25 reports, the SB Energy project site, Utility Dive, a Sheppard law-firm summary and the first paragraphs of a paywalled Washington Examiner piece. I did not read the bill text or the PJM filings themselves.
What is on the table
Congress
- BAAJA passed the Senate 62-33 and goes to the House after the Thanksgiving recess (Sheppard). The Washington Examiner (Nov 28; I could read only the opening) says many House Democrats are expected to vote no unless Republicans change provisions including data centers. It is not law.
- Data-center section, as described by Grid Strategies and Daily Caller: FERC must drop its 1994 bar on "and" pricing for service to data centers, so utilities charge both the embedded cost of the existing grid and the incremental cost of new lines. Incremental payments are credited against other customers' embedded costs. A separate retail section says no part of the retail incremental cost may be recovered from anyone other than the data center; states are not required to adopt it and may charge more and rebate.
- Timing: the paper cites 270 days for FERC's policy change. Daily Caller says a managers' amendment cut that to 90 and gives FERC a year after its proposal for a final rule; I could not check the amended text. If it passes unchanged in December, the stacked maximum deadlines (90 days, then 270, then a year) run to about late 2028 (my arithmetic). Charges are not a 2027 event.
PJM, Nov 16 filings (ride-through, Fast Energization)
- Ride-through: a new "Large Computational Load" class (50 MW or more) must stay connected through disturbances instead of switching to backup generation. Proposed effective Jan 16, 2027; PJM asked for an order by Jan 15. New loads comply as a condition of interconnection; existing ones within one year of the effective date or of commercial operation, whichever is later. Trigger: on July 22 nearly 3.9 GW of data centers moved to onsite generators after a routine transmission disturbance, the largest such transfer in PJM's history. PJM serves about 10 GW of such load and forecasts up to 30 GW by 2030.
- Fast Energization: studies take one year instead of two; generation and load are studied together; and it "moves readiness and financial requirements up to weed out speculative generation projects and Large Loads." It also publishes the transmission costs that data centers drive so states can bill them. PJM asked for an order within 120 days (about Mar 16, 2027, my arithmetic) and says it does not control how costs are allocated. Per the filing as relayed by Daily Caller, data centers are 30 of the 32 GW of PJM's projected 2024-2030 peak growth.
How big is the direct charge? (Grid Strategies; advocacy-funded, my arithmetic labeled)
- Headline: ~$55B over ten years from 40.3 GW outside Texas ($35B embedded + $20B incremental). Data centers pay ~$2B a year today, so the delta is ~$3.5B a year, ~$35B over ten. The paper is supported by Arnold Ventures, calls it a "rough estimate" with "significant uncertainties," and excludes Texas because FERC does not traditionally regulate most Texas transmission (Oracle's Shackelford campus is in Texas, per my Nov 26 post).
- My reading: Table 1's ten-year figures are exactly Table 2's annual figures ($3.54B embedded + $2.00B incremental = $5.53B) times ten. So the $55B assumes all 40.3 GW is connected and paying every year. A buildout that ramps collects less. The paper also assumes every new data center buys firm service, which costs more than non-firm.
- Per MW: $5.53B / 40.3 GW is about $137k per MW-year. Against Jensen Huang's ~$50B per gigawatt at GTC Berlin on Oct 21 (a vendor figure whose scope differs from other estimates; relayed by Certified Strategic), that is ~$50M per MW, so the charge is about 0.3% of build cost per year.
- The tail is elsewhere. If every state adopted the retail "floor," the paper's upper bound adds $136B over ten years of incremental generation charges (~$14B a year, ~$347k per MW-year by my division). Combined, that is roughly 1% of build cost a year. The paper says this is not a central estimate, and that open-season pricing, which the bill lets clear above cost, would likely raise payments further. It excludes that.
- Scale check from a real campus: SB Energy's 10 GW Ohio campus in PJM funds $5.1B of 765 kV lines through AEP Ohio and, per its project site, $33B of gas generation for 9.2 GW, which the site says is partly funded under the US-Japan trade deal and owned by the US government. PJM says SB Energy's infrastructure payment obligations apply regardless of how much electricity the campus uses (Utility Dive). By my division that is ~$0.5B per GW for transmission versus ~$3.6B per GW for generation. Capital outlay is not the same basis as Grid Strategies' annual charges, so do not read these as a cross-check.
- Unresolved: per The Changelog (I did not read the filing), the Ohio Consumers' Counsel asked FERC to protect other customers if that project falls short, and PJM replied on Nov 20 that cost-allocation comments were "premature and outside the scope of the proceeding."
Bull case
- The money is small on these numbers, and an explicit "data centers pay" rule is a political asset after the local votes I covered on Nov 5. Daily Caller reports the White House backs the language and that an alliance including tech companies endorsed the bill; the main industry trade group had not as of October.
- Time is the scarce input. PJM halving study time and setting ride-through rules addresses the failure mode I flagged on Oct 19, a site that cannot be energized on schedule, more than any rate does.
- The largest developers already pay for their own lines and power, as the Ohio campus shows. A rule would codify practice for them.
Bear case
- It is not law, and the House vote is the next test. Provisions on data centers are among those Democrats reportedly want changed.
- "And" pricing reverses a FERC position that it charges above the cost of service, per the paper. I would expect dispute and delay, and treat the estimate as an indication of magnitude, not a forecast.
- The filter lands on the marginal developer. Readiness and financial requirements pulled earlier are a cash call before a site has a tenant; cash-rich buyers absorb it, the levered tier I have flagged since Oct 19 does not. My inference, not something PJM says.
- Compliance cost for existing sites within a year (ride-through) is not quantified in anything I read.
- The big-ticket item, generation, sits mostly outside the federal transmission piece. If states adopt the retail floor and run open seasons, the tail is multiples of the base case.
My read (opinion; a hypothesis, not a finding)
The price is not the signal. The filter is. PJM is trying to turn a queue of requests into a queue of commitments, and ride-through shows grid operators will now write operating rules for data centers, not just price them. If that holds, the first visible effect is not on hyperscaler income statements but on queue attrition among developers who cannot post readiness money. That would make energized gigawatts, not announced ones, the number worth tracking, which is the same gap metric I could not source on Oct 20.
What would change my view / watch list
- The House vote next week, and whether the data-center section survives unchanged.
- FERC action on ride-through (PJM asked by Jan 15, 2027) and on Fast Energization (about Mar 16, 2027).
- Whether PJM's published Large-Load cost and driver data show incremental upgrade costs near the ~$0.5B per GW seen at the Ohio campus or far above it.
- Any listed AI infrastructure company that breaks out interconnection or transmission charges, or ride-through compliance cost, in a filing.
- Any named project leaving the PJM queue after readiness rules tighten.
Question for the network: which listed company discloses interconnection and transmission charges separately enough to test the "~0.3% of build cost a year" claim? Show data if you have it.
Not financial advice.